Capacity, supply chain, and footprint
Can we make and move enough: comparing demand with capacity along the chain, fixing the link that limits it at the lowest cost, and choosing where to place capacity.
17 min
What this case type is and when it shows up
A capacity or supply-chain case asks whether the company can make and move enough to meet demand, and where to add or place capacity. Like operations, it is about finding the one link that limits the whole chain.
The underlying theory, in plain language
Lay the chain out (supply of inputs, production, storage, transport, demand) and compare the capacity of each link with the demand flowing through it. The link with the smallest capacity relative to demand limits the whole chain.
Required utilization is demand divided by capacity. A link that would need more than 100 percent cannot meet demand; one close to 100 percent has no room for peaks.
Footprint questions (where to build or place capacity) compare cost to serve: the cost to make a unit at each location plus the cost to deliver it to customers. A cheap plant far from demand can cost more per delivered unit than a dearer plant close by. Resilience and access to suppliers also matter.
What the prompts sound like, from simple to hard
- Simple: can our one plant in Vietnam meet next year's demand.
- Medium: which link in the chain will break first as demand grows 15 percent.
- Hard: where to place a new warehouse to serve growing Gulf markets at the lowest cost to serve.
Build the structure from the goal
Three moves that give you the structure
- Start from the decision. Can the client meet demand, and what is the cheapest way to add the capacity it lacks: where, and owned or rented?
- Write the maths of the goal. Units delivered = the lower of demand and the capacity of each link (suppliers, production, storage, transport). For a location choice: cost per unit served = production + handling + delivery, and a new site pays when the saving per unit x volume covers its fixed cost.
- Let the business pick the branches. Which link breaks first depends on the product. Heavy, low-value goods such as water or cement are limited by transport cost and distance. Fresh and frozen food is limited by cold storage and time. Online retail is limited by warehouse space and delivery promises.
- Which link limits summer deliveries?
- Production lines per day
- Key: Cold storage: pallets of space
- Refrigerated trucks
- Fixes: rent cold storage for the peak, or build
This comes from units delivered = the lower of demand and each link. Frozen food must stay cold at every step, so cold storage is the likely limit.
- Cost per car delivered from each site
- Labour and energy cost per car
- Key: Shipping and import duties to the main markets
- Suppliers nearby
- Fixed cost of the plant and break-even volume
Same maths, a location choice. For cars, duties and shipping can outweigh labour savings, so the cost of reaching the main markets leads.
Why a generic structure scores lower
Assuming the factory is the limit because it is the most visible part of the chain misses the link that actually breaks. The score goes to the candidate who checks every link against demand.
Crack any case in five movesFinding and narrowing the real problem
Compare each link's capacity with demand and lead with the one that limits the chain, rather than assuming the factory is the limit because it is the most visible. Then compare fixes on cost.
Names you may hear, kept as questions that fall out of the goal maths
- Chain capacity scan: Which link has the least capacity compared with demand? Where it stops helping: Capacities and demand shift with the seasons; one snapshot can mislead.
- Cost to serve by location: What does each unit cost to make and deliver from each site? Where it stops helping: Soft factors such as resilience and supplier access matter too.
- Make, buy, or rent capacity: Is it cheaper to own the capacity or to use a third party, given how steady demand is? Where it stops helping: Third parties add flexibility but reduce control.
Methods for solving this type
- Map the chain and its link capacities
- Compare each with demand
- Find the limiting link and the value of the shortfall
- Compare fixes on cost
- Place capacity where cost to serve is lowest
The math patterns it relies on
- Demand versus capacity per link
- Required utilization = demand / capacity
- Lost units x contribution
- Cost to serve = production cost + delivery cost per unit
Worked cases
Worked case
Which link breaks first, and the cheapest fix
Case
A bottled-water company in Indonesia, which reports in US dollars, expects demand of 1,000,000 cases next year. Its plant can make 1,200,000 cases, but its own trucks can move only 900,000, and each case earns USD 2 of contribution. It could hire a third-party logistics firm at USD 0.60 per case, or run more trucks of its own for USD 150,000 a year, adding 150,000 cases of transport capacity. The capacity of each link in its supply chain is in the table. The operations director asks whether it can meet demand, and what the best fix is.
Interviewer-led: the interviewer shows the chain table and asks which link breaks, what it costs, and which of two fixes to choose.
The companies and figures in this case are made up for practice, unless a source is named.
Questions to ask
Situation
What does the company sell, and where?
What the interviewer says
Small bottles of drinking water, packed in cases of 24 and sold to supermarkets and small shops in and around Jakarta.
History
Has transport been a limit before?
What the interviewer says
No. Demand grew about 10 percent this year, and the truck fleet has not grown in three years.
Objective
What is the goal?
What the interviewer says
Meet next year's demand at the lowest cost.
Financials
What does each case earn?
What the interviewer says
About USD 2 of contribution, after production costs and before any extra transport cost.
Market
Is demand even across the year?
What the interviewer says
It peaks in the dry season, but assume even demand for now. The monthly pattern is in the second exhibit.
Customers
Could we sell unmet demand later?
What the interviewer says
No. Customers switch to other brands.
Competitors
Who are the rivals?
What the interviewer says
One large international brand and many local brands. Small shops stock whichever brand arrives.
Operations
What are the options for more transport?
What the interviewer says
A third-party logistics firm would charge USD 0.60 per case. More trucks of our own would cost USD 150,000 a year and add 150,000 cases of capacity.
Can bottle and cap suppliers keep up?
What the interviewer says
Yes. They can support 1,500,000 cases a year.
How are the trucks used today?
What the interviewer says
Each truck makes two delivery runs a day, six days a week. City traffic makes a third run impossible.
Is the water source a limit?
What the interviewer says
No. The spring licence allows far more than the plant can bottle.
Constraints
Are there any constraints on the fix?
What the interviewer says
New trucks would be leased for at least three years. The board wants a decision this quarter.
Exhibits
Exhibit 1
| Link in the chain | Capacity next year (cases) | Demand next year (cases) |
|---|---|---|
| Bottle and cap supply | 1,500,000 | 1,000,000 |
| Production (plant) | 1,200,000 | 1,000,000 |
| Transport (own trucks) | 900,000 | 1,000,000 |
Exhibit 2
| Months | Demand (cases a month) | Transport capacity (cases a month) | Plant capacity (cases a month) |
|---|---|---|---|
| Four dry-season months | 100,000 | 75,000 | 100,000 |
| Eight other months | 75,000 | 75,000 | 100,000 |
Source: illustrative company forecast.
Solution
Show the solutionHide the solution
Hypothesis
The plant has spare capacity, so my hypothesis is that transport, not production, is the limit, and that renting transport is cheaper than owning more.
Structure
- Compare each link with demand, then compare fixesThis comes from cases delivered = the lower of demand, production capacity, and transport capacity; each fix is judged on its cost.
- Production versus demand
- Key: Transport versus demand
- Fix: third-party logistics or own trucks
Analysis
1. Production
Capacity of 1,200,000 against demand of 1,000,000, so production has spare capacity.
Production slack (cases): 1,200,000 - 1,000,000 = 200,000
2. Transport
Transport can move 900,000 against demand of 1,000,000.
Transport shortfall (cases): 1,000,000 - 900,000 = 100,000
3. Required utilization of transport
Meeting demand would need the trucks to run above 100 percent of capacity, which is impossible.
Required transport utilization (%): 1,000,000 ÷ 900,000 × 100 = 111
4. Cost of doing nothing
100,000 cases of lost sales at USD 2 of contribution each.
Lost contribution (USD): 100,000 × 2 = 200,000
5. Fix A: third-party logistics
Move the 100,000 extra cases at USD 0.60 each.
Net gain with third party (USD): 100,000 × (2 - 0.6) = 140,000
6. Fix B: own trucks
The extra trucks cost USD 150,000 a year but only 100,000 of their 150,000 cases of capacity are needed.
Net gain with own trucks (USD): 100,000 × 2 - 150,000 = 50,000
7. When would owning trucks win?
Third-party transport would cost as much as the trucks only at this many cases, more than the 150,000 the trucks can carry.
Cost-equal volume (cases): 150,000 ÷ 0.6 = 250,000
8. Check the seasons
The second exhibit drops the even-demand shortcut. Demand is 100,000 cases a month in the four dry months and 75,000 in the other eight, while trucks move 75,000 a month. The whole shortfall falls in the dry months, and the plant runs at full capacity then. Extra trucks would add only 12,500 cases a month, half the dry-month gap, which makes owning trucks look worse still.
Dry-season transport shortfall (cases): (100,000 - 900,000 ÷ 12) × 4 = 100,000
- Exhibit 1: Only transport is below demand, so it is the link that limits the chain; supply and production have spare capacity.
- Exhibit 2: All of the transport shortfall falls in the dry months, when the plant also runs at full capacity.
Recommendation
Hire a third-party logistics firm for the extra volume, and do not add production. First, we can make enough but cannot move enough: transport falls 100,000 cases short, which would lose USD 200,000 of contribution. Second, the third party costs about USD 60,000 and keeps USD 140,000 of profit, against a net USD 50,000 from running more of our own trucks. At USD 0.60 per case, renting stays cheaper for any shortfall the extra trucks could carry. Third, the shortfall sits entirely in the four dry months, so trucks bought for it would stand idle for eight months a year. The move in play is buying flexible capacity instead of owning it. Water is cheap to make but bulky to move, and demand is seasonal, so a cost paid per case suits the business better than a fixed fleet. Production and bottle supply already have spare capacity, but the plant runs at its limit in the dry months, so check the peak before demand grows further.
Risks
- Third-party capacity may be scarce in the peak season
- Service quality from a third party may be harder to control
Next steps
- Get quotes from two logistics firms with peak-season guarantees
- Model the dry-season peak month by month
Strong and weak answers
A strong candidate
Checked every link, found transport was the limit, valued the shortfall, and compared two fixes on cost.
A weak candidate
Recommended a bigger factory, which already had spare capacity.
Worked case
Where should a Gulf online retailer put its next warehouse?
Case
A Dubai-based online retailer of home goods serves customers in the UAE and Saudi Arabia from one warehouse in Dubai. That warehouse will be full in two years. Saudi customers already complain that delivery takes four days. The chief executive asks whether to expand in Dubai or open a new warehouse in Riyadh.
Candidate-led: you set up a cost-to-serve comparison and ask for the costs; the interviewer answers what you ask.
The companies and figures in this case are made up for practice, unless a source is named.
Questions to ask
Situation
What does the retailer sell?
What the interviewer says
Furniture, kitchenware and home decor, through its own website and app.
History
How has it grown?
What the interviewer says
Total orders grew by about a fifth to a quarter each year for the last two years. Saudi orders now outnumber UAE orders; the history is in the exhibit.
Objective
What matters most: cost or delivery speed?
What the interviewer says
Cost first, but Saudi customers complain about four-day delivery.
Financials
What does a Saudi order cost us today?
What the interviewer says
Handling in Dubai is AED 12 an order, and cross-border trucking plus customs is AED 28.
What would a Riyadh site cost?
What the interviewer says
AED 15 an order to handle and AED 10 for local delivery. It would cost AED 18 million a year to run and AED 30 million one time to set up.
Market
Where are the customers?
What the interviewer says
About 1.5 million orders a year in the UAE and 2 million in Saudi Arabia, and Saudi orders are growing faster.
Customers
Would faster delivery sell more?
What the interviewer says
Tests suggest about 10 percent more Saudi orders with one-day delivery, at AED 45 of contribution each.
Are returns a problem?
What the interviewer says
Returns are about 5 percent of orders, much the same in both countries.
Competitors
What do rivals offer in Saudi Arabia?
What the interviewer says
Two large marketplaces deliver next day in Riyadh and Jeddah from local warehouses.
Operations
How full is the Dubai warehouse?
What the interviewer says
It handles 3.5 million orders a year and reaches its limit of about 4.5 million in two years.
How are UAE orders delivered?
What the interviewer says
Next day from Dubai. UAE customers do not complain about speed.
Constraints
Are there rules to check for a Saudi site?
What the interviewer says
It needs a commercial licence and must meet local hiring quotas. Check the current rules with local advisers.
Exhibits
Exhibit 1
| Year | UAE orders (millions) | Saudi orders (millions) |
|---|---|---|
| Two years ago | 1.1 | 1.2 |
| Last year | 1.3 | 1.6 |
| This year | 1.5 | 2 |
Source: illustrative company data.
Exhibit 2
| Site | Handling (AED per order) | Delivery to the customer (AED per order) | Fixed cost of the site (AED m a year) |
|---|---|---|---|
| Dubai, today | 12 | 28 | Already paid |
| Riyadh, new site | 15 | 10 | 18 |
Source: illustrative company estimates.
Solution
Show the solutionHide the solution
Hypothesis
Shipping every Saudi order across the border adds trucking and customs cost to each order. My hypothesis is that a Saudi warehouse lowers cost to serve enough to cover its fixed cost, and also speeds up delivery.
Structure
- Cost to serve Saudi orders from each locationThis comes from cost per order = warehouse handling + delivery for each site; a new site needs enough orders to break even on its fixed cost.
- Per-order cost: warehouse handling plus delivery
- Key: Fixed cost of a new site and break-even orders
- Payback of the setup cost
- Speed and resilience
Analysis
1. Serve Saudi from Dubai
Candidate: "What does a Saudi order cost us today?" Interviewer: "Handling in Dubai is AED 12 an order, and cross-border trucking plus customs is AED 28."
Cost per Saudi order from Dubai (AED): 12 + 28 = 40
2. Serve Saudi from Riyadh
Interviewer: "A smaller Riyadh site would cost AED 15 an order to handle, and local delivery AED 10."
Variable cost per order from Riyadh (AED): 15 + 10 = 25
3. Yearly cost from Dubai
2 million Saudi orders at AED 40.
Yearly cost, Dubai option (AED): 2,000,000 × (12 + 28) = 80,000,000
4. Yearly cost from Riyadh
Candidate: "What does the Riyadh site cost to run?" Interviewer: "AED 18 million a year in rent, staff, and systems."
Yearly cost, Riyadh option (AED): 2,000,000 × (15 + 10) + 18,000,000 = 68,000,000
5. Break-even orders
The Riyadh site saves AED 15 an order, so it needs this many Saudi orders a year to cover its fixed cost. Today's 2 million is well above it.
Break-even Saudi orders a year: 18,000,000 ÷ ((12 + 28) - (15 + 10)) = 1,200,000
6. Payback
Interviewer: "Setting up Riyadh costs AED 30 million one time." Candidate: "At AED 12 million saved a year, that pays back in two and a half years."
Payback (years): 30,000,000 ÷ (80,000,000 - 68,000,000) = 2.5
7. Upside from faster delivery
Candidate: "Would one-day delivery sell more?" Interviewer: "Tests suggest about 10 percent more Saudi orders, at AED 45 of contribution each." Candidate: "I will treat that as upside, not as part of the case."
Extra contribution from faster delivery (AED a year): 2,000,000 × 0.1 × 45 = 9,000,000
- Exhibit 1: Saudi orders grew about two thirds in two years, against about a third for the UAE, so the growth is in Saudi Arabia.
- Exhibit 2: Riyadh costs more to handle each order but far less to deliver it, against a new fixed cost.
Recommendation
Open a warehouse in Riyadh rather than expanding in Dubai. First, it cuts the cost of a Saudi order from AED 40 to AED 25, saving about AED 12 million a year after its AED 18 million of running costs. Second, it breaks even at 1.2 million Saudi orders a year, well below today's 2 million. It pays back its AED 30 million setup in about two and a half years. Third, one-day delivery could add about AED 9 million a year of contribution, and a second site makes the business less exposed to a single warehouse or border crossing. The move in play is a regional network design: put stock close to the larger, faster-growing market. In online retail, delivery and border costs are a large part of each order's cost, so the warehouse location sets the margin. Keep the Dubai site for UAE orders, which frees space there.
Risks
- Saudi order growth could slow, although the site covers its costs down to 1.2 million orders
- Licensing and hiring in a new country may delay the opening; check current rules
- Handling costs at a new, smaller site may start higher than planned
Next steps
- Shortlist three sites in Riyadh and get rent and labor quotes
- Confirm the current licensing steps for a Saudi warehouse with local advisers
- Plan which products to stock in Riyadh first
Strong and weak answers
A strong candidate
Compared the full cost to serve from each location, found the break-even volume and payback, and kept the speed benefit as upside rather than relying on it.
A weak candidate
Chose to expand in Dubai because handling there is cheapest per order, ignoring the AED 28 of cross-border cost on every Saudi order.
Prompt: "Can we meet next year's demand?"
Weaker answer
Assumes the factory is the constraint and proposes expanding it, ignoring that transport is the real limit.
Stronger answer
Compares each link with demand, finds transport limits the chain, values the lost sales, and picks the cheaper of two transport fixes.
Why the stronger answer wins: The strong answer checks the whole chain and prices the fix. The weak one fixes the most visible link instead of the limiting one.
Common mistakes, traps, and curveballs
- Assuming production is the limit when transport or supply is
- Building capacity that an upstream link cannot feed
- Ignoring seasonal peaks
- Choosing a fix without comparing its cost with the alternatives
- Placing capacity far from where demand is growing
How firms often vary on this type
These cases are often quantitative and reward careful exhibit reading. Expect a table of capacities and a clear limiting link to find. Formats differ by office and change over time, so check the current process for your target office.
Practice
Plant A in Saudi Arabia makes a unit for SAR 3.0 and ships it to customers for SAR 2.0. Plant B makes it for SAR 3.5 and ships it for SAR 1.0. What is the lower cost to serve per unit, in SAR?
A warehouse in Jeddah runs at 85 percent of its capacity. Demand grows by 20 percent. What utilization would it need, in percent?
A truck in Malaysia carries 1,200 cases per trip, and a trip costs SGD 900 through a Singapore-based carrier. What is the transport cost per case, in SGD?
Quick check
Required utilization is 70 percent for production, 98 percent for warehousing, and 80 percent for trucks. Demand will grow 10 percent. Which link breaks first?
Quick check
A plant can make 150 units a day, but its only supplier can deliver inputs for 120. Demand is 140 units a day. What limits output?
Quick check
Plant X makes a unit more cheaply than Plant Y, but is far from customers. How should you compare them?
The one thing to remember
Find the link that limits the chain by comparing each with demand, then choose the cheapest fix for that link.
Next module: Investment and capital project decisions
Sources
Math checked, facts checked against sources on 16 June 2026.
- Recognized public explanations of case-interview concepts and terms
Spotted something wrong or out of date? Report a mistake. We check every report and correct the page.