A parts factory in Vietnam moves from big batches to flow

Worked case with 14 questions and 1 exhibit

Case

A factory in Bac Ninh, Vietnam makes 2,000 electronic parts a day. It runs big batches, so about 40,000 half-finished parts sit between steps. Each is worth USD 5 of materials and work, and finance puts the carrying cost at 22 percent a year. Making small batches and passing them straight on would cut the pile to 10,000 parts. What does flow gain? (Fictional factory, illustrative figures.)

The companies and figures in this case are made up for practice, unless a source is named.

Questions to ask

Situation

  • What does the factory make?

    What the interviewer says

    Small connectors for two phone assemblers nearby. Output is steady at 2,000 parts a day.

  • Who runs the plant?

    What the interviewer says

    A plant director who joined two years ago from a car parts plant in Korea.

History

  • Why does it run big batches?

    What the interviewer says

    Changeovers on the presses took 3 hours until last year. A project cut them to 30 minutes, but batches stayed at 5,000 parts.

  • Have quality problems been costly?

    What the interviewer says

    Last year a fault at the first step went unnoticed for 15 days. By then 30,000 parts had been made with it, and all were scrapped.

Objective

  • What does the director want?

    What the interviewer says

    To free cash and offer shorter delivery times. The larger customer has asked for orders to arrive in under 10 days.

Financials

  • What is a part worth?

    What the interviewer says

    A finished part sells for USD 8. A half-finished part holds about USD 5 of materials and work on average.

  • How is the 22 percent carrying cost built up?

    What the interviewer says

    Finance uses 10 percent for the cash tied up, 6 for space and handling, 4 for damage and scrap, and 2 for insurance.

Market

  • Is demand growing?

    What the interviewer says

    Volume is flat at 2,000 parts a day. Phone models change every year, so each part design lasts about 12 months.

Customers

  • How concentrated are the customers?

    What the interviewer says

    Two customers take 70 percent and 30 percent of output.

Competitors

  • What do rivals offer?

    What the interviewer says

    A rival in Thai Nguyen promises 7-day delivery. A large rival in Shenzhen competes mainly on price.

Operations

  • What are the steps?

    What the interviewer says

    Five: stamping, plating, moulding, assembly and test. Plating is the slowest, at 2,200 parts a day.

  • Where does the stock sit?

    What the interviewer says

    The exhibit with this case shows the parts waiting before each step, today and with flow.

Constraints

  • Are there limits on what can change?

    What the interviewer says

    No new machines this year. Workers are paid a monthly wage, not by the batch.

  • Does the factory need the floor space back?

    What the interviewer says

    Not now. The stock fills about 1,200 square metres, and no new product line is planned.

Exhibit

Exhibit 1

Half-finished parts waiting before each step (parts)
Half-finished parts waiting before each step (parts)
Waiting beforeTodayWith flow
Plating12,0004,000
Moulding10,0002,000
Assembly10,0002,000
Test8,0002,000
Total40,00010,000

Source: illustrative.

Solution

Show the solution

Structure

  • Gains from flow: lead time, cash freed, yearly carrying cost
    • Lead time = parts in the system / parts finished a day (Little's Law)
    • Key: Cash freed = parts removed x value per part
    • Yearly saving = cash freed x carrying cost

Analysis

  1. 1. Lead time before

    40,000 parts in the system, 2,000 finished a day.

    Lead time before (days): 40,000 ÷ 2,000 = 20

  2. 2. Lead time after

    10,000 parts in the system, still 2,000 a day.

    Lead time after (days): 10,000 ÷ 2,000 = 5

  3. 3. Cash freed

    30,000 fewer parts at USD 5 each, released once.

    Cash freed (USD): (40,000 - 10,000) × 5 = 150,000

  4. 4. Yearly saving

    22 percent of the stock no longer held.

    Carrying cost saved a year (USD): 150,000 × 0.22 = 33,000

  5. 5. What last year's late fault cost

    A fault at the first step went unnoticed for 15 days, so 15 days of parts were scrapped at USD 5 each.

    Scrap from the late-found fault (USD): 15 × 2,000 × 5 = 150,000

  6. 6. The same fault with flow

    With 5 days in the system, the fault shows up at test within about 5 days. Scrap from one such fault falls by two thirds.

    Scrap avoided on one fault (USD): (15 - 5) × 2,000 × 5 = 100,000

  7. 7. Buffer before the bottleneck

    Keep 4,000 parts in front of plating, the slowest step, so a short stop upstream does not starve it.

    Buffer before plating (days of output): 4,000 ÷ 2,000 = 2

  • The exhibit: Flow cuts every pile but keeps the largest one in front of plating, the slowest step.

Recommendation

The factory should move to flow, because it cuts the time a part spends in the factory from 20 days to 5. It frees USD 150,000 of cash once. It also saves about USD 33,000 a year in carrying cost (the yearly cost of holding stock). The bigger gains are often hidden. With 5 days in the system, a fault at the first step is found in days, not weeks. This means far fewer parts are made wrong. And the factory can promise customers shorter delivery times. The risk is a breakdown. With little stock between steps, one stopped machine stops the line. So keep a small buffer of stock in front of the bottleneck. The quality gain alone is large: last year's late fault scrapped USD 150,000 of parts, and flow would have saved about USD 100,000 of that. Parts makers for phones win orders on delivery time and quality, so a 5-day lead time beats the 10 days the larger customer asks for.

Risks

  • With little stock between steps, a breakdown upstream of plating can stop output within hours
  • Small batches mean more changeovers; if they creep back above 30 minutes, plating loses output
  • Staff used to long runs may resist the change, so output can dip in the first weeks

Next steps

  • Start with one product family and cut its batch size from 5,000 to 500 parts
  • Keep about 2 days of output (4,000 parts) in front of plating and watch it daily
  • Track lead time, half-finished stock and scrap every week
  • Offer the larger customer a shorter delivery promise once lead time holds near 5 days