Should a warehouse near Rotterdam automate its picking?
Worked case with 14 questions and 1 exhibit
Case
An online retailer's warehouse near Rotterdam, the Netherlands, employs 50 pickers at EUR 50,000 a year each. It is weighing a system that brings shelves to the pickers. The system costs EUR 3 million installed, lasts about 10 years and costs EUR 200,000 a year to run. At the planned volume it does the work of 16 pickers, and staff turnover is 20 percent a year. Should the retailer buy it? (Fictional company, illustrative figures.)
The companies and figures in this case are made up for practice, unless a source is named.
Questions to ask
Situation
What does the warehouse ship?
What the interviewer says
Home and garden goods ordered on the retailer's own website, to customers in the Netherlands, Belgium and Germany. 50 pickers work across two shifts.
Who leads operations?
What the interviewer says
A new operations director who joined from a carmaker last year.
History
How has volume moved?
What the interviewer says
The exhibit with this case shows orders shipped each year. Orders grew about 25 percent a year for three years, then 4 percent last year.
Objective
What does management want?
What the interviewer says
A lower cost per order. Its rule is that projects must pay back within 6 years.
Financials
What does a picker cost?
What the interviewer says
EUR 50,000 a year each, including taxes and benefits.
What does the system cost to own?
What the interviewer says
EUR 3 million installed and EUR 200,000 a year for maintenance, software and energy. It lasts about 10 years.
What return does the company need on capital?
What the interviewer says
Finance uses 8 percent a year. At that rate, EUR 1 a year for 10 years is worth about EUR 6.71 today.
Market
What volume does the plan assume?
What the interviewer says
Growth of 8 percent a year. The 16-picker saving is based on that plan.
Customers
Are there seasonal peaks?
What the interviewer says
In November and December orders run about 40 percent above the yearly average. Temporary staff cover the peak today.
Competitors
Have rivals automated?
What the interviewer says
A rival warehouse in Venlo installed a similar system last year.
Operations
Can the system handle every item?
What the interviewer says
About 85 percent of items. Bulky goods such as garden furniture must still be picked by hand.
How many pickers leave each year?
What the interviewer says
Turnover is 20 percent a year, so about 10 pickers.
Constraints
Are there rules on changing staff numbers?
What the interviewer says
Any change in staffing must be discussed with the works council. That usually takes about 3 months.
How long is the building lease?
What the interviewer says
It runs for 12 more years, with an option to extend.
Exhibit
Exhibit 1
Line chart: Orders shipped from the warehouse each year (millions of orders). Values in millions of orders. 5 years ago: 1.28; 4 years ago: 1.6; 3 years ago: 2; 2 years ago: 2.5; Last year: 2.6; This year, plan: 2.8.
Source: illustrative.
Solution
Show the solutionHide the solution
Structure
- Payback = one-off cost / (labour saved minus running cost)
- Yearly net saving at the planned volume
- Payback against a 10-year life
- Key: Volume risk: the saving if volume is lower
- People: can turnover absorb the change?
Analysis
1. Labour saved
16 pickers at EUR 50,000.
Labour saved a year (EUR): 16 × 50,000 = 800,000
2. Net saving
Minus EUR 200,000 a year to run the system.
Net saving a year (EUR): 16 × 50,000 - 200,000 = 600,000
3. Payback
EUR 3 million divided by EUR 600,000 a year.
Payback (years): 3,000,000 ÷ 600,000 = 5
4. At half the volume
If orders come in at half the plan, the system replaces only 8 pickers, but still costs EUR 200,000 a year to run.
Payback at half volume (years): 3,000,000 ÷ (8 × 50,000 - 200,000) = 15
5. Volume needed to pay back within its life
To repay EUR 3 million in 10 years it must save EUR 300,000 a year net. So it must save EUR 500,000 of labour, which is 10 pickers out of the planned 16.
Share of planned volume needed (fraction): ((3,000,000 ÷ 10 + 200,000) ÷ 50,000) ÷ 16 = 0.625
6. People who leave anyway
20 percent of 50 pickers leave each year.
Pickers leaving a year: 50 × 0.2 = 10
7. Time to absorb 16 roles
16 roles, with 10 people leaving a year on their own.
Years to absorb the change through turnover: 16 ÷ 10 = 1.6
8. At three quarters of the volume
The system replaces 12 pickers instead of 16.
Payback at 75 percent of volume (years): 3,000,000 ÷ (12 × 50,000 - 200,000) = 7.5
9. Value today at the planned volume
At 8 percent a year, EUR 1 a year for 10 years is worth about EUR 6.71 today. Ten years of EUR 600,000, minus the price.
Net present value at plan (EUR): 600,000 × 6.71 - 3,000,000 = 1,026,000
10. Value today at half the volume
Ten years of EUR 200,000 net saving, minus the price.
Net present value at half volume (EUR): (8 × 50,000 - 200,000) × 6.71 - 3,000,000 = -1,658,000
11. Volume needed once money has a cost
The yearly net saving must be EUR 3 million / 6.71. Add running cost, turn it into pickers, and compare with 16.
Share of planned volume needed at 8 percent (fraction): ((3,000,000 ÷ 6.71 + 200,000) ÷ 50,000) ÷ 16 = 0.8089
- The exhibit: Growth slowed from 25 percent a year to 4 percent last year, while the plan assumes 8 percent.
Recommendation
Buy it only if the retailer is confident volume will stay above about 80 percent of plan. At the planned volume it saves EUR 600,000 a year and pays back in 5 years. That is inside the 6-year payback rule set by management, and well inside the 10-year life of the system. But it is a bet on volume. At half the plan, payback stretches to 15 years, longer than the system lasts. It needs about 62.5 percent of planned volume just to repay its cost. That is before allowing for the time value of money, which makes the bar higher. On people, turnover (staff leaving on their own) is 10 pickers a year. That can absorb the 16 roles in about 1.6 years if hiring is paused. Some pickers can also be retrained to run and maintain the system. Next step: test the volume forecast and agree the staffing plan with employee representatives before signing. At an 8 percent cost of capital, the system is worth about EUR 1.03 million today at plan. It needs about 81 percent of planned volume to break even. This automation move swaps variable wages for a fixed cost, which raises operating leverage. Warehouses with steady, growing volume gain most; last year orders grew only 4 percent, so that forecast is the key test.
Risks
- Volume falls or shifts to items the system cannot handle
- Breakdowns stop picking entirely unless some manual capacity is kept
- Pausing hiring for about 19 months strains the remaining team in peak season
- About 15 percent of items, such as garden furniture, still need manual picking, so the saving may fall short of 16 pickers
Next steps
- Rebuild the volume forecast from last year's 4 percent growth, not the earlier 25 percent
- Check how many of the 16 roles come from items the system can handle
- Open talks with the works council early, since they take about 3 months
- Plan the November and December peak with temporary staff for the first year