Which risks should a food factory in Johor pay to reduce?

Worked case with 14 questions and 2 exhibits

Case

A biscuit factory in Johor, Malaysia makes about MYR 15 million of profit a year and is weighing three ways to cut risk. A second flour supplier (MYR 0.4 million a year) would cut the loss if the main supplier fails from MYR 8 million to 2 million. An oven spare parts kit (MYR 0.15 million a year) would halve the loss from a breakdown. Flood insurance (MYR 1.2 million a year) would pay MYR 40 million of a MYR 50 million flood loss. Which should it take? (Fictional company, illustrative figures.)

The companies and figures in this case are made up for practice, unless a source is named.

Questions to ask

Situation

  • What does the factory make?

    What the interviewer says

    Biscuits and wafers for supermarkets in Malaysia and Singapore. It has one plant with one main oven line.

  • Who manages risk today?

    What the interviewer says

    Each risk has an owner on the management team. The CEO joined from a bank two years ago.

History

  • Have any of these risks happened before?

    What the interviewer says

    The main flour supplier missed deliveries for two weeks three years ago. The oven broke down three times in the last ten years. The estate has had two serious floods in 100 years.

Objective

  • What does the board want?

    What the interviewer says

    To protect profit and keep the company safe from any single event.

Financials

  • How strong is the balance sheet?

    What the interviewer says

    Profit is about MYR 15 million a year. Cash is MYR 20 million and bank debt is MYR 30 million.

  • What makes up the MYR 50 million flood loss?

    What the interviewer says

    The second exhibit breaks it down.

Market

  • How is demand?

    What the interviewer says

    Steady, growing about 3 percent a year. Exports to Singapore are 30 percent of sales.

Customers

  • What happens if the factory cannot deliver?

    What the interviewer says

    Two supermarket chains take half of sales. Each can give the shelf space to a rival after a few weeks of missed deliveries.

Competitors

  • Who are the rivals?

    What the interviewer says

    A larger maker in Penang with two plants, and imported brands from Indonesia.

Operations

  • Why would an oven breakdown cost MYR 2 million?

    What the interviewer says

    The oven is the bottleneck and runs around the clock. Key spare parts come from Germany and take about 6 weeks.

  • How is flour bought?

    What the interviewer says

    One supplier provides 90 percent of the flour. A second mill offers a contract for 40 percent of volume, at MYR 0.4 million a year above today's cost.

  • Are other projects under way?

    What the interviewer says

    A new packaging line arrives next year, paid from this year's budget.

Constraints

  • What does the insurance cover?

    What the interviewer says

    One insurer has quoted MYR 1.2 million a year. It pays up to MYR 40 million, and the factory bears the first MYR 10 million.

  • Could the plant move off the flood plain?

    What the interviewer says

    Not within five years. The land is owned, and the oven line cannot be moved quickly.

Exhibits

Exhibit 1

The biscuit factory's risk register (MYR millions; chance in percent a year)
The biscuit factory's risk register (MYR millions; chance in percent a year)
RiskChance a year (percent)Impact if it happens (MYR millions)Expected loss a year (MYR millions)Owner
Main flour supplier fails1080.8Head of purchasing
Flood shuts the plant for months2501Plant manager
Oven breakdown (the bottleneck)3020.6Head of maintenance
Cyberattack stops ordering560.3Head of IT
Product recall3200.6Head of quality

Source: illustrative.

Exhibit 2

What a flood would cost the biscuit factory (MYR millions)

Waterfall chart: What a flood would cost the biscuit factory (MYR millions). Values in MYR millions. Rebuilding and new equipment, total: 30; Profit lost while the plant is shut, change: +10; Customers that do not come back, change: +10; Total flood loss, total: 50.

Source: illustrative.

Solution

Show the solution

Structure

  • For each action: expected loss saved compared with what the action costs
    • Expected loss = chance x impact, for every risk
    • Action pays on average if the expected loss it removes is more than its cost
    • Key: Survival test: could one event sink the company?

Analysis

  1. 1. Total expected loss

    Add the five expected losses.

    Expected loss a year (MYR millions): 0.1 × 8 + 0.02 × 50 + 0.3 × 2 + 0.05 × 6 + 0.03 × 20 = 3.3

  2. 2. Second supplier: loss removed

    Expected loss falls from 10 percent x 8 to 10 percent x 2.

    Expected loss removed (MYR millions): 0.1 × 8 - 0.1 × 2 = 0.6

  3. 3. Second supplier: net

    Minus its MYR 0.4 million a year.

    Net gain a year, second supplier (MYR millions): 0.1 × 8 - 0.1 × 2 - 0.4 = 0.2

  4. 4. Spare parts kit: net

    Impact halves from 2 to 1, so the expected loss falls by 30 percent x 1; minus the kit's cost.

    Net gain a year, spare parts (MYR millions): 0.3 × 2 - 0.3 × 1 - 0.15 = 0.15

  5. 5. Insurance: expected payout

    2 percent chance of a MYR 40 million payout.

    Expected payout a year (MYR millions): 0.02 × 40 = 0.8

  6. 6. Insurance: net

    Expected payout minus the premium.

    Net a year, insurance (MYR millions): 0.02 × 40 - 1.2 = -0.4

  7. 7. Survival test

    How many years of profit would a flood wipe out?

    Flood loss in years of profit: 50 ÷ 15 = 3.33

  8. 8. Flood loss against cash

    A MYR 50 million loss against MYR 20 million of cash leaves a gap the company would have to borrow.

    Flood loss above cash (MYR millions): 50 - 20 = 30

  9. 9. Survival with insurance

    The factory bears the first MYR 10 million, in years of profit.

    Uninsured flood loss in years of profit: (50 - 40) ÷ 15 = 0.6667

  10. 10. Expected loss after all three actions

    Take away what each action removes from the MYR 3.3 million total.

    Expected loss a year after the actions (MYR millions): 3.3 - 0.6 - 0.3 - 0.02 × 40 = 1.6

  11. 11. Net cost of the whole package

    The three actions cost MYR 1.75 million a year and remove MYR 1.7 million of expected loss.

    Net cost a year of all three (MYR millions): 0.4 + 0.15 + 1.2 - (0.6 + 0.3 + 0.8) = 0.05

  • Exhibit 1: The flood has the largest expected loss even though it is the least likely risk, because its impact is so large.
  • Exhibit 2: Only 30 million of the loss is physical damage; the rest is lost trade while the plant is shut and after.

Recommendation

Take all three, for different reasons. The second supplier and the spare parts kit pay for themselves on average. They gain about MYR 0.2 million and 0.15 million a year. The spare parts also protect the oven, which is the bottleneck. Flood insurance loses about MYR 0.4 million a year on average, as insurance almost always does. Insurers charge more than the expected payout to cover their costs and profit. Buy it anyway: a flood would wipe out more than three years of profit and could close the company. Expected value is the right guide for frequent, survivable risks; for rare, ruinous ones, protect survival first. Next, check whether flood barriers would cost less than the premium over time. Taken together, the three actions cost only about MYR 0.05 million a year net on average. With insurance, the worst flood costs the factory 10 million, about 0.67 years of profit, instead of 50 million against 20 million of cash. A single-plant food maker runs one oven line around the clock, so one event can stop all of its sales. The main risk is the insurer: cover can rise in price or shrink after a claim.

Risks

  • The insurer may raise the premium or cut cover after the next flood in the region
  • The second supplier's flour may need recipe trials before it can replace the main supplier
  • Risks are linked: a flood could also cut off the flour supplier and the spare parts route

Next steps

  • Get quotes from at least two more insurers before signing
  • Price flood barriers and compare them with 10 years of premiums
  • Trial the second mill's flour on one product now, so it is ready when needed
  • Review the register each quarter, with each owner reporting on their action