How much to bid for a toll road concession in India

Worked case with 11 questions and 2 exhibits

Case

An infrastructure fund is bidding for a 20-year toll, operate and transfer concession on a highway in India, paying the government a lump sum up front. The road carries 40,000 vehicles a day at an average toll of INR 150. Operations and maintenance cost INR 55 crore a year and barely change with traffic. The fund wants its money back within 8 years. Is a bid of INR 1,200 crore safe, and what if traffic is 25 percent below forecast?

The companies and figures in this case are made up for practice, unless a source is named.

Questions to ask

Situation

  • What is the asset?

    What the interviewer says

    A 120 kilometre, four-lane stretch of national highway with two toll plazas. The fund would collect tolls for 20 years, then hand the road back.

History

  • How has traffic grown?

    What the interviewer says

    About 6 percent a year over the last five years, to 40,000 vehicles a day today.

Objective

  • What return does the fund need?

    What the interviewer says

    Its committee wants its money back within 8 years from cash before tax and financing.

Financials

  • What do vehicles pay, and what does the road cost to run?

    What the interviewer says

    The average toll is INR 150 across all vehicles. Operations and maintenance cost INR 55 crore a year and barely change with traffic.

  • Are there big repair costs?

    What the interviewer says

    A major resurfacing costs about INR 60 crore and is due about every six years, so one falls within the first 8 years.

Market

  • How common are these deals?

    What the interviewer says

    The National Highways Authority of India had raised INR 58,265 crore through toll, operate and transfer deals by November 2025.

Customers

  • Who uses the road?

    What the interviewer says

    About 55 percent of vehicles are trucks and 45 percent cars. Trucks pay higher tolls, which is why the average is INR 150.

Competitors

  • Who else is bidding, and is there a rival route?

    What the interviewer says

    Two other funds, one backed by a foreign pension fund. A state expressway on a parallel route has been proposed but has no funding yet.

Operations

  • How are tolls collected?

    What the interviewer says

    Almost all vehicles pay electronically by FASTag, and lost tolls are under 1 percent.

  • What happens to the toll plaza staff?

    What the interviewer says

    The current staff come with the road. The fund may keep them or bring in its own operator.

Constraints

  • Can the fund set its own tolls?

    What the interviewer says

    No. Tolls rise each year by a set formula linked to inflation.

Exhibits

Exhibit 1

Yearly cash before tax and financing at three traffic levels (INR crore)

Bar chart: Yearly cash before tax and financing at three traffic levels (INR crore). Values in INR crore. Forecast, 40,000 vehicles a day: 164; 10 percent lower, 36,000: 142.1; 25 percent lower, 30,000: 109.25.

Illustrative figures. One crore is 10 million.

Exhibit 2

Highest bid that pays back within 8 years (INR crore)
Highest bid that pays back within 8 years (INR crore)
Traffic caseYearly cashHighest bidPayback on a 1,200 bid (years)
Forecast1641,3127.32
10 percent lower142.11,136.88.44
25 percent lower109.2587410.98

Illustrative. Before tax, financing and resurfacing.

Solution

Show the solution

Structure

  • Is the bid paid back in time = yearly cash from tolls minus costs, against the price paid
    • Toll revenue = vehicles per day x average toll x 365
    • Cash after operations and maintenance, which are mostly fixed
    • Payback = bid divided by yearly cash
    • Traffic risk: the low case

Analysis

  1. 1. Yearly toll revenue

    40,000 vehicles x INR 150 x 365 days, in crore (1 crore is 10 million).

    Toll revenue (INR crore): 40,000 × 150 × 365 ÷ 10,000,000 = 219

  2. 2. Cash after operations

    Take off INR 55 crore of operations and maintenance.

    Yearly cash before tax and financing (INR crore): 219 - 55 = 164

  3. 3. Payback at forecast traffic

    INR 1,200 crore divided by INR 164 crore a year.

    Payback, forecast traffic (years): 1,200 ÷ 164 = 7.32

  4. 4. Revenue if traffic is 25 percent lower

    30,000 vehicles a day at the same toll.

    Toll revenue, low case (INR crore): 30,000 × 150 × 365 ÷ 10,000,000 = 164

  5. 5. Payback in the low case

    Costs stay at INR 55 crore, so yearly cash falls to INR 109.25 crore.

    Payback, low traffic (years): 1,200 ÷ (164.25 - 55) = 10.98

  6. 6. Payback with one resurfacing

    A major resurfacing of about INR 60 crore falls inside the first 8 years.

    Payback with resurfacing, forecast traffic (years): (1,200 + 60) ÷ 164 = 7.68

  7. 7. Highest bid that pays back in 8 years, forecast traffic

    Eight years of INR 164 crore.

    Maximum bid at forecast traffic (INR crore): 164 × 8 = 1,312

  8. 8. Highest bid that pays back in 8 years, low case

    Eight years of INR 109.25 crore.

    Maximum bid at low traffic (INR crore): (164.25 - 55) × 8 = 874

  • Exhibit 1: With fixed costs, a 25 percent traffic fall cuts cash by a third.
  • Exhibit 2: A bid of INR 1,200 crore fails the 8-year test with only a 10 percent traffic miss.

Recommendation

A bid of INR 1,200 crore is not safe. It pays back in about 7.3 years at forecast traffic, but a traffic miss of only 10 percent pushes payback to about 8.4 years. If traffic is 25 percent lower, it takes about 11 years, well past the 8-year target. First, costs are mostly fixed, so a 25 percent fall in traffic cuts yearly cash by a third, from INR 164 crore to about INR 109 crore. Second, the fund carries all the traffic risk under this model, unlike a hybrid annuity road where the government pays. Third, one resurfacing of about INR 60 crore stretches payback to about 7.7 years, so the margin of safety is thin. The 8-year test supports a bid of INR 1,312 crore at forecast traffic but only INR 874 crore in the low case. This is a bid for an asset with traffic risk, so the bid should sit nearer the low case of INR 874 crore unless traffic evidence is strong. The risk is that a new parallel road or a change in toll rules cuts traffic for years. As a next step, check traffic counts at the toll plazas, planned roads nearby and the toll increase formula before setting the final bid.

Risks

  • A new free road or rail line can take traffic
  • Toll increases follow a formula linked to inflation, which may lag costs
  • Rival bidders with a lower cost of money may outbid a disciplined price

Next steps

  • Commission an independent traffic count at each toll plaza over several weeks
  • Find out whether the proposed parallel expressway has funding or a start date
  • Model the toll increase formula against expected inflation for the full 20 years