Protecting an e-bike maker from a magnet cut-off
Worked case with 11 questions and 1 exhibit
Case
A fictional e-bike maker in the Netherlands buys all its motors from one supplier in China. The motors depend on rare-earth magnets, and export licence delays have hit other buyers this year. The board has two options: hold extra stock of motors, or move part of the volume to a supplier in Japan. Which option creates more value?
The companies and figures in this case are made up for practice, unless a source is named.
Questions to ask
Situation
Tell me about the company.
What the interviewer says
A fictional e-bike maker in the Netherlands that makes 120,000 bikes a year and sells them across Europe.
History
Has supply ever been cut?
What the interviewer says
Not yet. Other buyers of rare-earth motors had shipments held up by export licence delays this year.
Objective
What does the board want?
What the interviewer says
To protect output at the lowest yearly cost.
Financials
What does each bike earn?
What the interviewer says
About EUR 400 of contribution per bike.
What do motors cost to buy and to hold?
What the interviewer says
EUR 150 each from the Chinese supplier. Holding stock costs 20 percent of its value a year.
Market
How likely is a cut-off?
What the interviewer says
The team puts the chance of a three-month cut-off at 15 percent a year.
Customers
What happens if bikes cannot be made?
What the interviewer says
Dealers sell rival brands in the spring peak, so most lost sales are gone for good.
Competitors
What is the Japanese supplier offering?
What the interviewer says
It would take 40 percent of the volume at EUR 20 more per motor. Qualifying and managing it costs EUR 300,000 a year.
Operations
How much output would the Japanese supplier protect?
What the interviewer says
In a cut-off it keeps 40 percent of output going.
Is anything else changing?
What the interviewer says
The company is launching a cargo bike model and moving to a new paint supplier next year.
Constraints
Is there space and cash for more stock?
What the interviewer says
Yes. The warehouse has room for three months of motors, and the bank has agreed to fund it.
Exhibit
Exhibit 1
| Option | Motors involved | Extra cost per motor (EUR) | Fixed yearly cost (EUR) | Share of output protected (%) |
|---|---|---|---|---|
| A: three months of buffer stock | 30,000 | 30 | 0 | 100 |
| B: 40 percent from Japan | 48,000 | 20 | 300,000 | 40 |
Illustrative. For the buffer, the extra cost per motor is the yearly holding cost of 20 percent of EUR 150.
Solution
Show the solutionHide the solution
Structure
- Value of a defence = expected loss avoided minus its yearly cost
- Expected loss today: chance x lost contribution
- Option A: buffer stock
- Option B: second supplier
Analysis
1. Bikes lost in a cut-off
Three months of output.
Bikes lost in three months: 120,000 ÷ 12 × 3 = 30,000
2. Loss if it happens
EUR 400 of contribution per bike.
Loss from a cut-off (EUR): 30,000 × 400 = 12,000,000
3. Expected loss
15 percent a year.
Expected yearly loss (EUR): 0.15 × 12,000,000 = 1,800,000
4. Option A cost
30,000 motors at EUR 150, held at 20 percent a year.
Yearly cost of the buffer (EUR): 30,000 × 150 × 0.2 = 900,000
5. Option A net value
The buffer covers the whole three months.
Net value of the buffer (EUR a year): 1,800,000 - 900,000 = 900,000
6. Option B cost
48,000 motors at EUR 20 more, plus EUR 300,000.
Yearly cost of the second supplier (EUR): 48,000 × 20 + 300,000 = 1,260,000
7. Option B net value
It saves 40 percent of the expected loss.
Net value of the second supplier (EUR a year): 1,800,000 × 0.4 - 1,260,000 = -540,000
8. Premium at which Option B pays
The loss it avoids, minus the EUR 300,000 to manage it, spread over 48,000 motors.
Highest premium per Japanese motor that breaks even (EUR): (1,800,000 × 0.4 - 300,000) ÷ 48,000 = 8.75
- The exhibit: The buffer costs more per motor but protects all output for three months, while Japan protects only two fifths.
Recommendation
The e-bike maker should build the three-month buffer now, which is worth about EUR 0.9 million a year. It should not yet move volume to the second supplier. On these numbers that loses about EUR 0.5 million a year. This is a supply resilience decision: each defence is worth the expected loss it avoids minus its yearly cost. First, an expected loss of EUR 1.8 million a year is large next to the buffer's EUR 0.9 million cost. Second, the second supplier costs EUR 1.26 million to avoid only EUR 0.72 million of expected loss. It would pay only if its premium fell from EUR 20 to below about EUR 8.75 a motor. The risk is a cut-off longer than three months, which the buffer would not cover. That is where a second source earns its place. As a next step, qualify the Japanese supplier on a small volume so it can scale up quickly. Also link the motor price to the NdPr oxide index (a market price for a key rare-earth material).
Risks
- A cut-off longer than three months would outlast the buffer
- Motors held in stock may go out of date if the design changes
- The chance of a cut-off is a judgement, and the answer changes if it is much higher
Next steps
- Build the three-month motor buffer before the next season
- Qualify the Japanese supplier on a small volume and ask for a lower premium
- Link the motor price to the NdPr oxide index