A value-for-money test: build it ourselves or use a PPP?
Worked case with 10 questions and 1 exhibit
Case
A regional government in a fictional country needs a new road and is choosing how to deliver it. Option 1: build it itself for USD 100 million now and pay USD 3 million a year to maintain it for 20 years. Option 2: a public-private partnership (PPP) partner builds and maintains it, and the government pays USD 10 million a year for 20 years, reduced if lanes are closed. At a 5 percent discount rate, the present value of USD 1 a year for 20 years is about 12.46. The transport minister asks which option costs less in present value.
The companies and figures in this case are made up for practice, unless a source is named.
Questions to ask
Situation
What is the road?
What the interviewer says
A 40 km dual carriageway linking the region's port to the national highway. It will be free to use.
What will the road be called?
What the interviewer says
It will be named after a local poet, chosen by the regional council.
History
How have the region's past road projects gone?
What the interviewer says
Its last three road projects ran 15 to 30 percent over budget and opened about a year late.
Objective
What does the minister want most?
What the interviewer says
The lowest whole-life cost, with the road open within four years.
Financials
What does each side pay to borrow?
What the interviewer says
The region borrows at about 5 percent. Bidders expect to pay about 8 percent, and that cost is already in the USD 10 million a year.
Market
Who did the traffic study?
What the interviewer says
A university transport department, two years ago.
Customers
How much traffic is expected?
What the interviewer says
About 25,000 vehicles a day, 30 percent of them trucks going to and from the port.
Competitors
How many firms would bid for the PPP?
What the interviewer says
Three groups have shown interest. Two have built and run similar roads in other regions.
Operations
How would lane closures be penalized?
What the interviewer says
The yearly payment falls by USD 50,000 for each day a lane is closed without agreement.
Constraints
Can the region borrow USD 100 million?
What the interviewer says
Only just. Its debt is close to the legal limit, and the build would use most of the room left.
Exhibit
Exhibit 1
Bar chart: Present value of each option (USD millions at 5 percent, illustrative). Values in USD millions, present value. Build in-house, on budget: 137.38; Build in-house, 20 percent overrun: 157.38; PPP: 124.6.
Solution
Show the solutionHide the solution
Structure
- Compare the present value of each option's payments
- Option 1: build cost now + PV of maintenance
- Option 2: PV of availability payments
- Key: Then test risks that are not in the numbers
Analysis
1. Option 1
USD 100 million now plus USD 3 million a year times 12.46.
Present value of option 1 (USD millions): 100 + 3 × 12.46 = 137
2. Option 2
USD 10 million a year times 12.46.
Present value of option 2 (USD millions): 10 × 12.46 = 125
3. Difference
Option 1 minus option 2.
PPP saving in present value (USD millions): 137.38 - 124.6 = 12.78
4. With a typical overrun
This is a make or buy choice, and the main risk the PPP transfers is overrun. The region's last three roads ran 15 to 30 percent over budget; test 20 percent.
Present value of option 1 with a 20 percent overrun (USD millions): 100 × 1.2 + 3 × 12.46 = 157
5. Build cost at which the options tie
Option 1 only wins if the road is built for less than the PPP's present value minus maintenance.
Build cost at which option 1 matches the PPP (USD millions): 124.6 - 3 × 12.46 = 87.22
- The exhibit: The PPP is cheaper even if the in-house build comes in on budget.
Recommendation
The government should use the PPP, because it costs about USD 12.8 million less in present value, USD 124.6 million against USD 137.38 million. The gap widens to about USD 32.8 million if the public build overruns by 20 percent, as the region's recent roads did. Building it in-house only wins if the road costs under about USD 87.2 million, which no recent project has achieved. Governments usually borrow more cheaply than private firms, so the PPP must save through better building and maintenance, not finance. Many governments run this comparison formally, often called a public sector comparator.
Risks
- A 20-year contract is hard to change if traffic or needs change.
- The PPP partner's higher financing cost is built into the yearly payment, so weak bidding could erase the saving.
- Payments are a long commitment that limits future budgets, even if they do not count as debt.
Next steps
- Run a competitive tender with at least three bidders and compare bids against the in-house cost.
- Write clear lane availability standards and payment cuts into the contract.
- Check how the yearly payments count against the region's borrowing limit.