A fixed fee project that runs over, and how value based pricing compares

Worked case with 11 questions and 2 exhibits

Case

Cedarway Consulting (fictional) agreed a fixed fee of USD 600,000 to redesign a Saudi retailer's buying process. It planned 2,000 team hours at a cost of USD 150 per hour (pay and benefits). The work took 25 percent more hours than planned. What was the planned margin, and the margin after the overrun? An alternative offer was 10 percent of the first year's savings, which turned out to be USD 8 million. Which deal would have earned more, and how should Cedarway price the next one?

The companies and figures in this case are made up for practice, unless a source is named.

Questions to ask

Situation

  • Who are Cedarway and the client?

    What the interviewer says

    Cedarway is a 150-person consulting firm with offices in Riyadh and Dubai. The client is a Saudi grocery chain with about 200 stores.

History

  • Why did the project run over?

    What the interviewer says

    The client's buying data sat in four systems, and a new product category was added halfway through. The work took 2,500 hours instead of 2,000.

Objective

  • What does the partner want to decide?

    What the interviewer says

    How to price the next buying projects. Two more retailers are in the pipeline.

Financials

  • What were the fee and the cost of the team?

    What the interviewer says

    A fixed fee of USD 600,000. Team time costs USD 150 an hour in pay and benefits.

  • What did the client save?

    What the interviewer says

    USD 8 million in the first year, confirmed by the client's finance team.

Market

  • How is consulting demand in the Gulf?

    What the interviewer says

    Source Global Research expected the Gulf market to grow about 12 percent in 2025 to over USD 8 billion. Reports in 2026 describe Saudi clients asking for lower rates, fee caps and pay tied to results.

Customers

  • How much does the client buy each year?

    What the interviewer says

    About USD 400 million of goods from about 1,500 suppliers.

Competitors

  • How do rivals price this work?

    What the interviewer says

    Several Riyadh firms now offer a share of savings, some with no fixed fee at all.

Operations

  • How was the team set up?

    What the interviewer says

    Five consultants for ten weeks at about 40 hours a week. The overrun added two and a half weeks.

  • Anything else about the project?

    What the interviewer says

    All final reports were delivered in Arabic and English, and the client's chief executive changed during the project.

Constraints

  • When do clients pay?

    What the interviewer says

    Large Saudi clients often pay 90 days or more after invoice.

Exhibits

Exhibit 1

Cedarway's fee under each model, by first-year savings (USD thousands)
Cedarway's fee under each model, by first-year savings (USD thousands)
SavingsFixed fee10 percent of savingsUSD 300,000 plus 5 percent
USD 4 million600400500
USD 6 million600600600
USD 8 million600800700

Illustrative figures. Cost of the hours actually worked: USD 375,000.

Exhibit 2

Project margin under each model at USD 8 million of savings (percent)(%)

Bar chart: Project margin under each model at USD 8 million of savings (percent). Fixed fee as planned: 50 percent; Fixed fee after the overrun: 37.5 percent; Floor plus 5 percent: 46.43 percent; 10 percent of savings: 53.13 percent.

Illustrative figures.

Solution

Show the solution

Structure

  • Project margin = fee minus the cost of the hours used
    • Cost of hours = hours used x cost per hour
    • Fixed fee: the fee stays the same when hours run over
    • Value based: fee = share of savings, whatever the hours

Analysis

  1. 1. Planned cost

    2,000 hours at USD 150.

    Planned cost (USD): 2,000 × 150 = 300,000

  2. 2. Planned margin

    Fee minus planned cost, as a share of the fee.

    Planned margin (fraction): (600,000 - 2,000 × 150) ÷ 600,000 = 0.5

  3. 3. Cost after the overrun

    25 percent more hours: 2,500 hours at USD 150.

    Actual cost (USD): 2,000 × 1.25 × 150 = 375,000

  4. 4. Margin after the overrun

    The fee does not move, so the extra cost comes out of margin.

    Actual margin (fraction): (600,000 - 375,000) ÷ 600,000 = 0.375

  5. 5. Value based fee

    10 percent of USD 8 million of savings.

    Value based fee (USD): 8,000,000 × 0.1 = 800,000

  6. 6. Value based margin with the same hours

    USD 800,000 minus the actual cost of USD 375,000.

    Value based margin (fraction): (800,000 - 375,000) ÷ 800,000 = 0.5313

  7. 7. Savings at which the two deals pay the same

    A 10 percent share equals USD 600,000 when savings are USD 6 million.

    Break-even savings (USD): 600,000 ÷ 0.1 = 6,000,000

  8. 8. A value fee with a floor

    A fixed USD 300,000 plus 5 percent of savings, at USD 8 million of savings.

    Fee with a floor (USD): 300,000 + 0.05 × 8,000,000 = 700,000

  9. 9. Margin on the fee with a floor

    USD 700,000 minus USD 375,000 of cost.

    Margin with a floor (fraction): (700,000 - 375,000) ÷ 700,000 = 0.4643

  10. 10. Downside: savings of only USD 4 million

    A pure 10 percent share pays USD 400,000; the floor deal pays USD 500,000. Cost stays USD 375,000.

    Margin with a floor at USD 4 million of savings (fraction): (300,000 + 0.05 × 4,000,000 - 375,000) ÷ (300,000 + 0.05 × 4,000,000) = 0.25

  • Exhibit 1: The floor deal gives up some upside to protect the downside.
  • Exhibit 2: The overrun cost the fixed fee 12.5 points of margin.

Recommendation

Cedarway should price its next buying project on value, with a floor. The fixed fee margin fell from 50 to 37.5 percent when hours ran 25 percent over. A 10 percent share of the USD 8 million savings would have paid USD 800,000, a margin of about 53 percent. First, the firm carried all the risk of extra hours under the fixed fee. Second, the savings were measurable, which is what value based pricing needs. The two deals pay the same at USD 6 million of savings. Third, a floor of USD 300,000 plus 5 percent of savings would have paid USD 700,000, a margin of about 46 percent. It still earns a 25 percent margin if savings halve to USD 4 million. A pure share would then earn only about 6 percent. This pricing move also fits Saudi clients, who now push for fees tied to results. The risk is that savings fall short and the fee falls with them. As a next step, agree how savings are measured before work starts.

Risks

  • Savings can be hard to measure and easy to dispute
  • A fee linked to results can tempt a firm to chase quick savings over lasting change
  • Waiting for a year of savings delays cash, and Saudi clients often pay late

Next steps

  • Write the savings baseline and measurement method into the next contract
  • Offer the next two retailers a floor of about half the fixed fee plus a share of savings
  • Track hours against plan weekly so overruns show early under any model