A residential project in Dubai: margin and the effect of an overrun
Worked case with 10 questions and 1 exhibit
Case
Harbrook Developers (a fictional company) plans 400 apartments in Dubai to sell at an average of AED 1.5 million each. Costs are land AED 120 million, construction AED 300 million, design, permits and fees AED 30 million, sales and marketing AED 30 million, and financing AED 30 million. Its last tower ran over budget, and the lender wants to see the downside before it lends. The CEO asks for the profit and margin, and what happens if construction costs run 10 percent over budget.
The companies and figures in this case are made up for practice, unless a source is named.
Questions to ask
Situation
How experienced is Harbrook?
What the interviewer says
It has completed three smaller towers. This would be its largest project.
How will it be marketed?
What the interviewer says
From a showroom in a large mall, with a model apartment designed by an award-winning architect.
History
How did its last tower go?
What the interviewer says
Construction ran 12 percent over budget, mostly because of steel and labor costs.
Objective
What return does the board require?
What the interviewer says
A margin of at least 12 percent on every project.
Financials
How will the project be funded?
What the interviewer says
A bank will lend half of the construction cost. Buyer payments cover much of the rest as work progresses.
Market
How have prices moved?
What the interviewer says
Prices in the area rose strongly over the past three years. Agents report fewer viewings this year.
Customers
Who buys these apartments?
What the interviewer says
About 60 percent of buyers are investors who plan to rent the units out. The rest will live in them.
Competitors
What else is being built nearby?
What the interviewer says
Two other developers will launch about 1,500 apartments within 2 km in the next 18 months.
Operations
How long will it take to build?
What the interviewer says
About 30 months from start to handover.
Constraints
What contract options are there?
What the interviewer says
The contractor offers a fixed price of AED 315 million, or a cost-plus contract based on the AED 300 million budget.
Exhibit
Exhibit 1
Bar chart: Project profit under four scenarios (AED million, illustrative). Values in AED million. On budget: 90; Fixed-price contract: 75; 10 percent construction overrun: 60; Overrun and 10 percent lower prices: 0.
Solution
Show the solutionHide the solution
Structure
- Profit = sales revenue minus total development cost
- Revenue = units x average price
- Cost = land + construction + fees + sales + financing
- Sensitivity: construction overrun
- Key: Protection: fixed-price contract and pre-sales
Analysis
1. Revenue
400 apartments at AED 1.5 million.
Revenue (AED million): 400 × 1.5 = 600
2. Total cost
Add all cost lines.
Total cost (AED million): 120 + 300 + 30 + 30 + 30 = 510
3. Margin
Profit of 90 divided by revenue.
Margin (percent): (600 - 510) ÷ 600 × 100 = 15
4. Profit with a 10 percent construction overrun
Construction rises by 30 million.
Profit after overrun (AED million): 600 - 510 - 300 × 0.1 = 60
5. Overrun and a price fall together
Developers are highly geared to price and cost. With 1,500 new apartments launching nearby, test a 10 percent price fall on top of the overrun.
Profit with an overrun and a 10 percent price fall (AED million): 600 × 0.9 - 510 - 300 × 0.1 = 0
6. A fixed-price contract
The contractor offers a fixed price of AED 315 million, 5 percent above budget, and carries the overrun risk itself.
Profit with the fixed-price contract (AED million): 600 - (510 - 300 + 315) = 75
7. Margin with the fixed price
AED 75 million on AED 600 million of sales.
Margin with the fixed-price contract (percent): 75 ÷ 600 × 100 = 12.5
- The exhibit: Paying AED 15 million for a fixed price protects the board's margin floor.
Recommendation
Harbrook should go ahead, but on the fixed-price contract and with strong pre-sales. The project earns AED 90 million, a 15 percent margin. A 10 percent construction overrun cuts profit by a third, to AED 60 million, below the board's 12 percent floor. If sale prices also fell 10 percent, profit would fall to zero. Construction is AED 300 million of the AED 510 million cost, so paying AED 15 million to fix it locks in AED 75 million, a 12.5 percent margin.
Risks
- Weak sales: 1,500 competing apartments nearby could force price cuts.
- A fixed-price contractor may cut quality or fail if its own costs rise.
- Investor buyers may walk away from off-plan purchases if prices fall.
Next steps
- Check how much has been pre-sold, and aim for at least half before construction starts.
- Check the contractor's finances and past delivery before signing a fixed price.
- Test the margin at sale prices 5, 10 and 15 percent lower.