Standard: Should a city switch to electric buses?
Worked case with 11 questions and 2 exhibits
Case
A large city plans to replace 1,000 diesel buses. An international development bank asks whether electric buses make financial sense. The exhibit compares costs per bus. What do you recommend?
Difficulty: Standard. Format: interviewer-led, with an exhibit. Industry: Public sector and transport. Region: Global (a large city in a middle-income country). Interview length: about 30 minutes. The company is fictional and all figures are illustrative.
The companies and figures in this case are made up for practice, unless a source is named.
Questions to ask
Situation
What does the fleet look like today?
What the interviewer says
1,000 diesel buses, about 11 years old on average, running from six depots.
History
Has the city tried electric buses?
What the interviewer says
A one-year trial of 10 electric buses ran with 97 percent availability, about the same as diesel.
Objective
What does the city want?
What the interviewer says
Replace the fleet at the lowest total cost over the buses' life, and cut air pollution in the city center.
Financials
How long are buses used?
What the interviewer says
About 12 years each.
Who pays, and at what interest rate?
What the interviewer says
The city, with a loan from an international development bank at about 5 percent. The city's own borrowing costs about 8 percent.
Market
What are bus prices doing?
What the interviewer says
Electric bus prices have fallen about 30 percent in five years (illustrative). Diesel bus prices are flat.
Customers
How many people ride the buses?
What the interviewer says
About 1.5 million trips a day. Fares cover about half of operating costs.
Competitors
How many suppliers could bid?
What the interviewer says
At least four bus makers. Two offer eight-year battery warranties.
Operations
Is power available for charging?
What the interviewer says
Yes, at the city's depots, with new charging equipment.
Can electric buses cover the routes?
What the interviewer says
They run about 250 km on a charge. About 90 percent of routes need under 220 km a day.
Constraints
How fast can depots be ready?
What the interviewer says
The grid company needs about 18 months to upgrade the connection at each depot. Drivers need no new license.
Exhibits
Exhibit 1
| Cost item | Diesel bus | Electric bus |
|---|---|---|
| Purchase price | 250 | 450 |
| Fuel or electricity a year | 50 | 20 |
| Maintenance a year | 20 | 12 |
| Charging equipment (one time) | 0 | 50 |
Exhibit 2
| Year | Diesel | Electric | Electric, battery replaced in year 7 |
|---|---|---|---|
| Purchase | 250 | 500 | 500 |
| Year 4 | 530 | 628 | 628 |
| Year 8 | 810 | 756 | 856 |
| Year 12 | 1,090 | 884 | 984 |
Source: illustrative figures for practice, from the cost per bus in the first exhibit.
Solution
Show the solutionHide the solution
Hypothesis
Electric buses cost more to buy but less to run. My hypothesis is that over 12 years they are cheaper in total, and the real problem is financing the higher upfront cost.
Structure
- Total cost of ownership over 12 years
- Purchase and charging equipment
- Energy or fuel and maintenance each year
- Key: Total cost per bus and for the fleet
- Upfront financing need
Analysis
1. Diesel bus over 12 years
Purchase plus 12 years of fuel and maintenance (USD thousands).
Diesel total (USD thousands): 250 + 12 × (50 + 20) = 1,090
2. Electric bus over 12 years
Purchase, charging equipment, and 12 years of power and maintenance.
Electric total (USD thousands): 450 + 50 + 12 × (20 + 12) = 884
3. Saving per bus
Diesel total minus electric total.
Saving per bus (USD thousands): (250 + 12 × (50 + 20)) - (450 + 50 + 12 × (20 + 12)) = 206
4. Upfront gap for the fleet
Extra upfront cost per bus (purchase plus charging, minus the diesel price) for 1,000 buses, in USD million.
Extra upfront cost (USD million): 1,000 × ((450 + 50) - 250) ÷ 1,000 = 250
5. Payback of the extra upfront cost
The yearly running saving per bus is the difference in fuel and maintenance.
Payback (years): 250 ÷ ((50 + 20) - (20 + 12)) = 6.58
6. Curveball: battery replacement
Interviewer: "Engineers expect each battery to need replacing once, in year 7, at about USD 100 thousand." The undiscounted saving falls to USD 106 thousand per bus, and payback of the extra spending becomes:
Payback including the battery (years): (250 + 100) ÷ ((50 + 20) - (20 + 12)) = 9.21
7. Discounted at 5 percent
Interviewer: "At 5 percent, USD 1 a year for 12 years is worth about 8.86 today, and USD 1 in year 7 about 0.71." Net present value per bus of switching:
NPV at 5 percent (USD thousands): 38 × 8.86 - 250 - 100 × 0.71 = 15.68
8. Discounted at 8 percent
Interviewer: "At 8 percent, the factors are about 7.54 and 0.58." The year-7 battery now tips the answer negative:
NPV at 8 percent (USD thousands): 38 × 7.54 - 250 - 100 × 0.58 = -21.48
9. Fleet value at the development-bank rate
For 1,000 buses at 5 percent, the gain from switching is, in USD thousands:
Fleet NPV at 5 percent (USD thousands): 1,000 × (38 × 8.86 - 250 - 100 × 0.71) = 15,680
- Exhibit 1: Electric buses cost USD 250 thousand more upfront including charging, but save USD 38 thousand a year to run.
- Exhibit 2: Electric overtakes diesel in year 7 without a battery replacement, but only in year 10 with one.
Recommendation
I recommend switching to electric buses, but only with low-cost, long-term financing and battery protection. First, before discounting, an electric bus costs about USD 884 thousand over 12 years against USD 1,090 thousand for diesel. Second, one battery replacement cuts the saving to about USD 106 thousand per bus. At a 5 percent development-bank rate switching is worth about USD 16 thousand per bus, but at 8 percent it loses about USD 21 thousand per bus. Third, the USD 250 million extra upfront cost therefore needs a long, low-rate loan. At the development bank's 5 percent the whole fleet gains about USD 15.7 million; at the city's own 8 percent it would lose value. Phase the switch depot by depot, in step with the 18 months the grid company needs for each depot. The economics of electric fleets are the reverse of diesel: high upfront cost, low running cost, so the cost of capital decides the answer. The strategic move is therefore a financing one as much as a technology one. It needs cheap long-term debt, battery warranties that cover the year-7 replacement, and a tender among at least four suppliers.
Risks
- Electricity prices may rise
- Charging depots need reliable grid supply
- Staff need training to maintain electric buses
Next steps
- Run a pilot with 50 buses on two routes
- Tender with battery warranties and service terms
Strong and weak answers
A strong candidate
Compared total cost over the life of the bus, found the upfront gap, and matched financing to the running savings.
A weak candidate
Compared purchase prices only and rejected electric buses as too expensive.